An £8.5m joint open procurement for whole house retrofit

An £8.5m joint open procurement for whole house retrofit

CYD PROCUREMENT® | CASE STUDY

An £8.5m joint open procurement for whole house retrofit, taken from appointment to signed contract in under four months to meet a Welsh Government funding deadline.

The challenge

In late 2022 the Welsh Government confirmed three years of Optimised Retrofit Programme (ORP3) funding for every social landlord in Wales, £4.6m of it for Grŵp Cynefin. Contracts had to be signed by the end of March 2023, and the money came with a clear expectation that it would support local jobs and training. No existing framework was built around the communities Grŵp Cynefin serves, and its Tenants’ Working Group had set five priorities for any procurement: value for money, buying locally, quality, timescale and sustainability.

What Cyd did

Cyd was appointed on 6 December 2022 to design and run a tailored open procedure advertised on Sell2Wales, as a joint procurement with North Wales Housing so both landlords shared one contract and the cost of buying it. We wrote the full tender pack, led the evaluation with both landlords’ teams and issued the award. After award, Cyd challenged the winning bidder’s social value offer line by line so every commitment was measurable, and set up monthly reporting against it.

  • Procurement strategy: a tailored open procedure in place of a framework
  • Specification across six work streams, from PAS 2035 services to heat pumps and solar PV
  • SSQ, quality, price and social value forms, and an amended JCT Measured Term Contract
  • Evaluation and moderation with both landlords’ evaluators
  • Award, standstill and feedback to unsuccessful bidders
  • Social value clarification and monthly KPI reporting after award

At a glance

The same model, elsewhere

Cyd’s founder first designed this approach for Flintshire County Council in 2021. Cyd has since used it for a £20m joint open procurement for Flintshire County Council and ClwydAlyn (2022 to 2026), and for retrofit procurement for Your Housing Group (SHDF Wave 2.1) and YorEnergy in Yorkshire. That work sits within a track record of more than £450m of contracts procured since 2011.